The difference between ProcessingStageId and CurrentProcessingStageId

Question

What is the difference between ProcessingStageId and CurrentProcessingStageId in the Task table of the FlexiCapture 12 database?

Answer

ProcessingStageId is the identifier of the processing stage during which a task was created. CurrentProcessingStageId is the identifier of the processing stage on which the task is currently being processed.

Was this article helpful?

0 out of 0 found this helpful

Have more questions? Submit a request

Comments

0 comments

Please sign in to leave a comment.

Recently viewed