What is the difference between ProcessingStageId and CurrentProcessingStageId in the Task table of the FlexiCapture 12 database?

Answer

ProcessingStageId is the identifier of the processing stage during which a task was created. CurrentProcessingStageId is the identifier of the processing stage on which the task is currently being processed.